Battlefield Projects

Everything we're working on for the building. Tap a project for its call list and details.

⚠ Needs attention

  • Evan: pick a paint color for your office ASAP so William can paint after the drywall (the nursery will likely just match what's already in use). Open Drywall + room paint →

⚠ Payments coming up

  • Reimburse Micheal $100 — he fronted it for William's deposit 11/3.
  • Upcoming: $800 to William, the rest of his $1,000 labor, when he finishes the drywall and paint.
  • Upcoming: $5,500 to Perry Hudson, the rest of his $11,000, when he finishes the soffit/fascia job.
  • Upcoming: $2,500 to Cooper Morgan (Morgan Restoration) for the gutters (half of $5,000), after Perry is on the books.

Projects

Carpet squaresCarpet tiles for the building, done in phases. Phase 1 (foyer and lobby) is finished; the auditorium is next.Auditorium tiles ordered 10/27 · ≈ $6,395 total17 of 25 steps doneOpen →ElectricalOutlets, wall drilling and power the other projects need. Rayburn (volunteer electrician) is helping.Breakers fine · Rayburn helping3 of 4 steps doneOpen →Gravel parking lot (front)Gravel the parking lot: crusher run base (done), #57 stone on top, and now finishing the rest of the lot while Rayburn's equipment is on site.#57 stone coming Mon 11/9 morning7 of 11 steps doneOpen →Sewer line to city sewerDig a new sewer line from the back of the building to the city sewer.Likely on city sewer already · smoke test never happened2 of 7 steps doneOpen →Soffit repairRepair soffit/fascia around the entire building.Perry started 11/2 — back soffit torn off · still waiting on his signed contract back17 of 23 steps doneOpen →Roof leakWater is coming through the roof into the hallway right before the fellowship hall.New · looking for a roofer0 of 1 steps doneOpen →LED lightingSwap old lights for LED as cheaply as possible.ACE Power free audit + TVA rebates0 of 2 steps doneOpen →Drywall + room paintNew drywall in Evan's office and the nursery, then painting both rooms. William is doing the drywall and the painting.William: drywall + paint · $200 deposit paid 11/3, $800 due at completion5 of 11 steps doneOpen →Mini split (Evan's office)Pull the old heater and AC out of Evan's office and put in a ductless mini split, powered off the existing 220V heater circuit.Picked the unit · William running the 220V0 of 4 steps doneOpen →PaintingPainters to quote the building.10 painters to call0 of 1 steps doneOpen →Front signSimple 2-sided sign for now (~$2k), nicer sign later. Try to sell the old one. The church decides.For now ≈ $800–2k · new lit ≈ $10–30k1 of 9 steps doneOpen →Screens & videoTwo big TVs up front and a confidence monitor, with SDI video from the balcony booth — plus a new SDI run to the nursery so they can stream the service there.Equipment arrived · outlet boxes bought · TVs still to buy3 of 7 steps doneOpen →WiFi networkUniFi WiFi for the whole building: one gateway, a PoE switch and 3 ceiling access points.Equipment in, Micheal setting it up · waiting on Ace Fiber install3 of 8 steps doneOpen →Baptistry heaterReplace the baptistry water heater. Plumber from Lexington coming.Little Giant 6HHL 6 kW · replacement on hand0 of 1 steps doneOpen →Chairs & pews~250 cheap chairs; sell the old pews. Low priority.Pews given away 10/29 (to Selmer, TN) · chairs ~$5-7.5k used2 of 6 steps doneOpen →Building & floor planRoom sizes, records, and floor-plan drawings.9,000 sq ft · built 19721 of 2 steps doneOpen →

Completed

Finished projects. Open one to see how it was done, who to call and prices for next time.

All to-dos

Carpet squares

  • ✓
    Measure, total + 20% overage
    Micheal · 7,274 sq ft measured; 8,729 sq ft to buy
    Done
  • ✓
    Find best price (compare 6+ suppliers)
    Micheal / Claude · Carpet USA options with live freight quotes are below. Cheapest inspected: Refurbished Gray Plank, $7,395 delivered
    Done
  • ✓
    Pick the tile for Phase 1
    Church · 10/14: Refurbished Gray Family Designer Plank
    Done
  • ✓
    Call Carpet USA: what does "refurbished" mean? (questions on the carpet page)
    Micheal · 10/14: older stock, never used, just dusted off. All brand new.
    Done
  • ✓
    Order Phase 1 tiles (309 tiles / 832 sq ft)
    Micheal · 10/14: Order #261683, $930.81 delivered (Ground Home Delivery). Receipt sent to Rock Solid.
    Done
  • ✓
    Ask Carpet USA to correct the shipping ZIP to 38834 (order shows 38835, the P.O. box ZIP)
    Micheal · Fixed by Micheal (10/15). Order #261683
    Done
  • ✓
    Carpet delivered (309 tiles)
    Evan / Micheal · Delivered by 10/16. FedEx 878709289348
    Done
  • ✓
    Buy the glue
    Micheal · 10/19: bought, $137. Works for carpet tile and vinyl.
    Done
  • ✓
    Pick an installer for Phase 1
    Micheal · 10/19: William (handyman) for $400 flat. CM Carpet's quote was $1,251.80.
    Done
  • ✓
    Buy the transition strip (carpet tile to vinyl)
    Micheal · Bought at Lesley's Floor Designs, about $16. Didn't work well where new tile meets the old carpet (piles too different); fine once the auditorium is tiled
    Done
  • ✓
    William installs Phase 1
    Micheal · Finished Sat 10/24. 4 days, 17 h 29 min total ($400 ≈ $22.90/hr)
    Done
  • After Phase 1: work out the auditorium price with William
    Micheal / William · He's willing to do it; rough guess about $2,200 for labor. Confirm the price before he starts
    To do
  • ✓
    Pay William for Phase 1 ($400)
    Church / RSM · Paid in full 10/24. Signed invoice #001 marked PAID: download at the top of this page
    Done
  • ✓
    Phase 2 (auditorium): confirm the price and freight in the Carpet USA cart (1,556 tiles, ZIP 38834)
    Micheal · Quoted $3,696.87 delivered (10/27)
    Done
  • ✓
    Fill the low spot in the slab before William carpets over it (Quikrete Concrete Repair)
    Micheal · Bought at Lowe's, about $9. Let it cure before gluing tile over it
    Done
  • Get the missing box of tiles (1 of 12 never arrived)
    Micheal · Carpet USA is asking their FedEx rep to find it; if not found they'll send a replacement box (10/27)
    Waiting
  • ✓
    Ask Carpet USA for a bulk discount on the auditorium order (about 4,200 sq ft / 1,556 tiles)
    Micheal · 10/27: $3,696.87 for 4,200 sq ft delivered
    Done
  • ✓
    Order the auditorium tiles: 1,556 Refurbished Gray Family Designer Plank (Carpet USA)
    Micheal · Ordered 10/27: $3,646.87 delivered ($3,318.95 + $327.92 freight). Paid by Rock Solid Ministries' card
    Done
  • Buy 4 pails of the carpet-tile glue (same as Phase 1)
    Micheal · About $137 a pail
    To do
  • Set the auditorium install dates with William
    Micheal · About $2,200 labor (his rough guess); church moves the pews and pulls the old carpet
    To do
  • Replacement tiles (20) for the odd-sized ones from Phase 1
    Carpet USA · Shipped 10/27, FedEx 879305037665 (added to order #261683). Check they're the right size when they arrive
    Waiting
  • Auditorium tiles delivered (1,556): check every box and that all tiles are the same size
    Evan / Micheal · Ships to Evan at the church
    To do
  • ✓
    Order tiles for the toddler room
    Micheal · 10/28: order #262419, 61 tiles, $221.62 ($91.51 shipping to be refunded; ships with #262379)
    Done
  • Ask William to add the toddler room to the auditorium install
    Micheal · 176 sq ft
    To do
  • Carpet USA: refund $91.51 shipping on #262419 and ship it with #262379
    Carpet USA · Emailed 10/28
    Waiting

Debris removal

  • ✓
    Haul the pile to the dump at 2664 S Harper Rd
    Micheal · 5 loads total, $107 (10/22: 3 at $20, 1 at $27; 11/4: 1 more at $20)
    Done

Electrical

  • ✓
    Rayburn walk-through: both breaker panels and the list on this page
    Micheal / Rayburn · 10/20: went great. Breakers are fine. Rayburn is helping with the TV outlets, the wall drilling and the gravel prep.
    Done
  • ✓
    Check the breakers
    Rayburn · 10/20: Rayburn says the breakers are fine, no issue.
    Done
  • ✓
    Decide on the auditorium lights: keep switching at the breakers, or add real switches
    Rayburn / church · 10/20: Rayburn says no issue.
    Done
  • Drill through the walls for the internet and coax runs (Rayburn's hammer drill)
    Rayburn / Micheal · Rayburn is bringing a hammer drill and bit
    To do

Gravel parking lot (front)

  • ✓
    Get 30 tons of crusher run delivered
    Micheal · 10/28: Bill Phillips came through; first load dumped. No need to call Buddy Ayers or JR's
    Done
  • Buy silt fence at Lowe's (for the dirt going on the berm)
    Micheal · Rayburn's request. Lowe's, 1800 South Parkway, (662) 287-9000 (Pro card), or Tractor Supply, 1983 Hwy 72 E, (662) 286-8117 (Tenax 3 ft × 100 ft ≈ $50). Ask Rayburn how many feet
    To do
  • ✓
    Bill Phillips: 2 loads of crusher run (10/28)
    Micheal · Delivered 10/28. Invoice #15912: 2 loads at $747.66 + 7% tax = $1,599.99. Paid 10/29 on Kristin's card
    Done
  • ✓
    Submit the 811 locate request (online at ms811.org)
    Micheal · Submitted online 10/20 at 12:11 PM (covers the front lot and the rear sewer trench). Screenshot on this page.
    Done
  • ✓
    Put the white flags or paint down: front lot and the sewer trench path
    Micheal · Done; the utilities marked by 10/23
    Done
  • ✓
    Utility marks: all 5 utilities responded (Ticket #26102012401223)
    Micheal · 10/23: AT&T + ACE clear; gas, water, sewer marked. OK to dig
    Done
  • Find private lines 811 won't mark (power to the old front sign, water, sewer)
    Rayburn / Micheal · 811 only marks up to the meter. Hand-dig near the paint marks
    To do
  • #57 stone on top of the crusher run (after it packs down and gets rained on)
    Micheal · Coming first thing Monday morning (11/9); Phillips will call Rayburn when the truck is on its way.
    To do
  • ✓
    Rayburn digs out the dirt with his backhoe
    Rayburn · 10/28: front cleared, crusher run spread
    Done
  • Finish the rest of the lot with Rayburn (beyond the original front-lot scope)
    Rayburn · Tom decided 11/2 to go ahead while Rayburn's equipment is still on site. Rough estimate from Rayburn: about $5,400. Waiting for the ground to dry out enough first.
    Waiting
  • ✓
    Call Bill Phillips: heads-up for 2 more crusher run loads + 3 loads of #57
    Micheal · Called 11/4. Phillips Sand and Gravel, (662) 284-6061. He's bringing the #57 first thing Monday morning (11/9) and will call Rayburn when he's on his way.
    Done

Sewer line to city sewer

  • Confirm with the city: are we already on city sewer?
    Micheal · 10/29: the smoke test never happened. Micheal thinks we're already on city sewer — call Corinth Gas & Water or the city to confirm for certain before closing this out
    To do
  • ✓
    Before the smoke test: run water in every drain (sinks, floor drains, baptistry drain) and tell anyone in the building
    Micheal · Not needed: the smoke test never happened
    Done
  • Find out who handles sewer at 170 MS-2 NE (Corinth Gas & Water, or a county utility) and ask what a connection takes
    Micheal · Permit, tap fee, inspection, who can make the tie-in
    To do
  • Find where the city sewer line runs behind the building (manhole, street or easement) and measure the trench length
    Micheal / Rayburn · Needed for the 811 ticket
    To do
  • Find out what the building uses now (septic tank?) and what has to happen to it
    Micheal · Usually pumped and filled or removed
    To do
  • ✓
    811 ticket for the sewer trench
    Micheal · Ticket #26102012401223 (same as the gravel). Expires 11/09; update 11/3–11/4, or file a new one if the trench is dug later.
    Done
  • Get the connection done (licensed plumber if the city requires it) and inspected
    Church
    To do

Soffit repair

  • ✓
    Get Perry's corrected contract ($11,000)
    Micheal · 10/28: final version received: $11,000, lift included, start by Mon 11/2, 7-10 working days, 1-year workmanship warranty, $15/LF for extra rotten wood, all white trim
    Done
  • ✓
    Get Perry's liability insurance
    Micheal · Received 10/30. Posted on this page (premium/address redacted).
    Done
  • ✓
    Tom Weaver signs Perry's contract (church side)
    Tom Weaver · 10/29: signed
    Done
  • Get Perry's signature on the contract
    Perry · Church side signed 10/29 by Tom Weaver; Perry's signature line is still blank
    To do
  • ✓
    Pay Perry $5,500 (half of $11,000) up front
    Church / RSM · Paid 10/31, check #5994. Receipt posted on this page.
    Done
  • Get Perry's projected finish date once he starts
    Micheal · Keep this updated as he works
    To do
  • Pay Perry the remaining $5,500 at completion
    Church / RSM · The rest of the $11,000, due when the job is finished
    To do
  • ✓
    Cooper: gutters-only estimate in writing ($5,000)
    Micheal · 10/28: estimate #1028, $5,000. Ask him to add footage, 6-inch, 20 downspouts, old-gutter removal
    Done
  • ✓
    Bobbie (Perry's gutter friend) to call about the gutters
    Micheal · Not needed: Cooper is doing the gutters
    Done
  • ✓
    Perry: agree to $11,000 for the fascia, trim and soffit, in writing
    Micheal · 10/28: Perry called back. Good at $11,000, and he rents the lift (not us)
    Done
  • ✓
    Cooper: waiting on answers to our questions
    Micheal · 10/28: Cooper withdrew the fascia offer; doing gutters only for $5,000
    Done
  • ✓
    Get Cooper's quote in writing (soffit/fascia about $10,000; with gutters about $15,000)
    Micheal · Received 10/26: estimate #1027, $15,000 (fascia + gutters). Download at the top
    Done
  • ✓
    Perry Hudson (Hudson Windows & Exteriors): written quote
    Micheal · Received 10/26: $14,500 (details below)
    Done
  • ✓
    Lift rental price
    Micheal · 50-ft boom lift, $1,580 for a week (also lets us power-wash). 10/28: Perry is renting it, so not our cost
    Done
  • ✓
    Questions for Perry before signing (list on this page)
    Micheal · 10/28: settled by phone; he's resending his quote
    Done
  • ✓
    Get a second quote to compare against $14,500
    Micheal · Morgan Restore (Cooper) came out 10/26: about $10,000, or $15,000 with gutters
    Done
  • ✓
    B&A Roofing and Gutters: quote requested through their website form
    Micheal · Filled out the form on 10/14. Waiting for them to reach out. Confirm they do soffit work (their Corinth page doesn't list it). (662) 205-0023 — not needed: we went with Perry Hudson
    Done
  • ✓
    Universal Apex Construction & Roofing: called and left a message
    Micheal · Called 10/14, left a message. Waiting for a call back. (662) 603-7170 — not needed: we went with Perry Hudson
    Done
  • ✓
    Have the coax and Cat6e cables ready before the soffit crew starts, so they go up inside the soffit
    Micheal · 11/2: not needed after all — found a way to run the AV cables inside the same wall from the booth to the TVs, instead of up through the soffit.
    Done
  • Power-wash the building while the lift is rented
    Micheal · Perry is renting the lift now; ask him if we can use it to power-wash while it's here. Same week as the lift. Wash before Perry puts up the new trim, or after he's done, so the new trim stays clean
    To do
  • Give Cooper about a week's notice before Perry finishes the fascia
    Micheal · Gutters go on after the new fascia
    To do
  • Pay Cooper $2,500 (half of $5,000) for the gutters
    Church / RSM · After Perry is on the books
    To do
  • ✓
    Received the $5,500 check for Perry
    Micheal · 10/29: check in hand
    Done

Roof leak

  • Find a roofer to look at the leak
    Micheal · Plan to ask Perry (soffit contractor) for a recommendation when he's out at the church.
    To do

LED lighting

  • Call ACE Power for the free lighting analysis and TVA EnergyRight eligibility
    Micheal · Called 10/13: left a message for Kevin at ACE Power. He'll call back if they can help.
    Waiting
  • Count fixtures by room (tube length, T12/T8, ballast, dimmers) with photos
    Micheal / Grok
    To do

Drywall + room paint

  • ✓
    Get Kevin's arrival date
    Micheal · Not needed: Kevin got sick 11/1 and he and his crew can't come. Looking for a new contractor instead.
    Done
  • Check out the Lowe's cart for the drywall materials
    Micheal · Added everything to the Lowe's cart 11/2 (about $964 with delivery, before tax) — two of the original items were out of stock/discontinued and got swapped for in-stock equivalents at the same spec. Just needs checkout.
    In progress
  • ✓
    Buy paint
    Micheal · Done — the foyer hallway and fellowship hall are already painted.
    Done
  • ✓
    Mask all the foyer trim before painting
    Volunteers · Done — the foyer hallway and fellowship hall are already painted.
    Done
  • ✓
    Find a new drywall contractor for Evan's office and the nursery
    Micheal · 11/2: William is doing it.
    Done
  • Get William's wife's name for the check
    Micheal · His payments need to be written to her, not him.
    To do
  • ✓
    Pay William $200 up front
    Micheal / RSM · Paid 11/3 in cash — $100 from selling the church's old Peavey board, $100 fronted by Micheal personally (needs reimbursing).
    Done
  • Get Evan's paint color choice for his office
    Micheal · Needed ASAP so William can paint after the drywall goes up. Nursery will likely just match the color already in use.
    To do
  • Buy paint for the nursery and Evan's office
    Micheal · Needed once colors are picked, before William gets to the painting.
    To do
  • Pay William the remaining $800 when he's done
    Micheal / RSM · Check made out to his wife (name still needed).
    To do
  • Reimburse Micheal $100 for William's deposit
    RSM · He fronted $100 of his own money for William's $200 deposit on 11/3.
    To do

Mini split (Evan's office)

  • Take out the old heater and AC unit in Evan's office
    William
    To do
  • Buy the TOSOT 12,000 BTU mini split ($809.99) and wall mount bracket ($39.99)
    Micheal · https://tosotdirect.com links on this page.
    To do
  • William runs the 220V up and out the wall where the AC is now
    William · Reusing the existing circuit that powers the old heater.
    To do
  • Check if fire-rated caulk/firestop is needed once the wall is open
    Micheal · Might need to run to Lowe's for it — won't know until the wall's open.
    To do

Painting

  • Call painters for quotes
    Micheal · Give everyone the same scope sheet
    To do

Front sign

  • ✓
    Measure the width across the top of the lower sign panel
    Micheal · 7½ ft right under the top box, tapering to 4 ft at the bottom.
    Done
  • Measure how deep the sign box edges are (top box and lower panel)
    Micheal · Over a couple of inches needs its own trim strips
    To do
  • Get the old sign appraised from photos
    Micheal · Liquid Fire Vintage Neon, Matthews Auctions
    To do
  • Try to sell the old sign (Facebook Marketplace, vintage-sign groups, auction)
    Micheal · Buyer handles removal
    To do
  • Price a simple 4×8 double-sided sign for now (~$2k budget)
    Micheal · Nickels Signs (662) 643-3193 vs. Logo Print Co. / Big Tex Banners online
    To do
  • Long-term: get 2–3 quotes for the nicer lit sign
    Micheal · Nickels (Corinth), Econo Signs, Signs First (Tupelo)
    To do
  • Get 1 restore quote to compare
    Micheal · Nickels or Frank Balton
    To do
  • Check permits with the city
    Micheal · Corinth Code Enforcement (662) 287-2401
    To do
  • Bring the quotes and any sale offer to the church to decide
    Micheal · The church makes the final call
    To do

Screens & video

  • ✓
    Pick up coax and Cat6 at Lowe's in Corinth
    Micheal · Bought 10/28; both are at the church. Southwire RG6 coax (item 3332782, $71.68) and Micro Connectors Cat6 outdoor white (item 5000887101, $125.99)
    Done
  • ✓
    Route the coax and Cat6e cable from the booth to the TVs
    Micheal · 11/2: found a way to run both cables inside the same wall the whole way, booth to TVs. Didn't need to go outside or wait on the soffit.
    Done
  • Put in 2 regular outlets in the wall behind the front TVs
    Rayburn / Micheal · Rayburn helping; found a way in through the attic. Outlet boxes bought 11/2.
    To do
  • ✓
    RSM team: order the equipment (everything but the TVs)
    RSM team · Ordered 10/28
    Done
  • Buy the TVs (2 front TVs + 65″ confidence monitor)
    Church · Picker on this page
    To do
  • Run additional SDI (coax) to the nursery so they can stream the service
    Micheal
    In progress
  • Pull power for the nursery SDI feed and behind the stage
    Micheal · Using the 2-gang new-work boxes for the Wago junctions along the way.
    In progress

WiFi network

  • Answer the picker questions with Evan (cameras, auditorium puck, outdoor WiFi, speakers)
    Micheal · On this page
    To do
  • Get the make and model of the mixer and the wireless snake
    Micheal · Decides the auditorium channel plan
    To do
  • Confirm the internet provider and where the modem comes into the building
    Micheal · Plan: fiber into the small office in the back wing (network room). Confirm the provider can bring it there
    To do
  • ✓
    Walk the building and mark 3 ceiling spots (auditorium, lobby/office, classroom wing) plus a spare 4th
    Micheal
    Done
  • ✓
    Run Cat6 from the switch to each spot (pull the 4th spare cable at the same time)
    Micheal · 11/2: Micheal ran all the puck cables and terminated them in the attic — nothing had to go outside.
    Done
  • ✓
    RSM team: order the WiFi gear (proposal at the top of this page)
    RSM team · Ordered 10/28 (Amazon, store.ui.com, B&H). Then set up Staff, Guest, AV networks
    Done
  • Walk-test signal on a phone; add the 4th access point only if there's a dead spot
    Micheal
    To do
  • Set up the UniFi gateway, switch and access points
    Micheal · All equipment is in from Amazon, store.ui.com and B&H. Putting it together now; still waiting on Ace Fiber to install the fiber line before it can go fully live.
    In progress

Baptistry heater

  • Plumber visit: swap the heater, check fittings and pump
    Micheal
    Waiting

Chairs & pews

  • ✓
    Pews: tried to sell, gave them away
    Micheal · 10/29: no buyers on Facebook, so given away; picked up, going to Selmer, TN (they'll resell individually later, ~$75-100 each)
    Done
  • Take an after photo of the auditorium without the pews
    Micheal · For the church history
    To do
  • Mark the Facebook Marketplace listing sold
    Micheal
    To do
  • Chairs: ask about UsedPews.org lots (120 @ $25, 215 @ $50) and Universal Hotel Liquidators ($19.95)
    Micheal · Low priority
    To do
  • ✓
    Pews: measure them and post the listing on Facebook Marketplace
    Micheal · 10/20: listed. 2 at 18′7″ × 2′10″ high × 1′9″ deep; choir pews 21 ft and 25 ft. Not getting responses on Facebook, so also listed on UsedPews (10/21).
    Done
  • Take down the UsedPews.org listing (#11191)
    Micheal · Pews given away 10/29 (no buyers on Facebook)
    To do

Building & floor plan

  • ✓
    Pull county parcel / building records
    Claude · 1972, 9,000 sf, 2.76 ac. No floor plan online
    Done
  • Walk-through sketch of room positions so we can draw a real layout
    Micheal / Grok · Room sizes are known; positions are not yet
    To do

Real money spent

Actual payments made so far (not budgets or estimates). Running total below.

DateProjectWhatAmount
10/14Carpet squaresPhase 1 carpet tiles (Carpet USA #261683)$930.81
10/22Debris removalDump runs, 4 loads at 2664 S Harper Rd (3 at $20, 1 at $27)$87.00
10/24Carpet squaresPhase 1 install, William (invoice #001)$400.00
10/27Carpet squaresAuditorium carpet tiles (Carpet USA #262379)$3,646.87
10/28Carpet squaresToddler room carpet tiles (Carpet USA #262419, incl. $91.51 shipping expected to be refunded)$313.13
10/28Screens & videoAV equipment (Amazon)$687.48
10/28Screens & videoCoax cable (Lowe's)$71.68
10/28WiFi networkUniFi equipment (Amazon, store.ui.com, B&H) + Cat6 cable (Lowe's)$826.94
10/29Gravel parking lot (front)Crusher run, 2 loads (Phillips Sand and Gravel #15912)$1,599.99
10/31Soffit repairDeposit to Perry Hudson (check #5994)$5,500.00
11/3Drywall + room paintWilliam's $200 deposit (drywall/paint) — $100 from selling the church's old Peavey board, $100 fronted by Micheal personally$200.00
11/4Debris removalDump run, 1 load at 2664 S Harper Rd$20.00
Total spent$14,283.90

Committed, not paid yet

Signed contracts and accepted estimates we owe, but haven't paid out yet. Rough guesses that haven't been confirmed yet are in “Looking ahead” below instead.

ProjectWhatDueAmount
Soffit repairRemaining balance to Perry Hudson (of his $11,000 contract)At completion$5,500.00
Soffit repairGutters, Cooper Morgan / Morgan Restoration (estimate #1028, accepted)After Perry is on the books$5,000.00
Drywall + room paintWilliam's labor (drywall + paint, Evan's office and the nursery)At completion$800.00
Drywall + room paintDrywall materials (ToughRock, Gold Bond, mud, tape, screws, ladder) — Lowe's cart readyAt checkout$1,038.94
Gravel parking lot (front)Finishing the rest of the lot: 2 more crusher run loads + 3 loads of #57 stone (Phillips), Rayburn's digging/spreading laborPhillips delivering Mon 11/9 morning; Rayburn finishing after$5,400.00
Total committed$17,738.94

Looking ahead

Rough estimates and known-but-not-yet-ordered costs — prices can change before these are locked in.

ProjectWhatNoteAmount
Screens & video2 front 98" TVs (TCL Q6) + 65" confidence monitor (Hisense)Picked options on the AV page; not bought yet.$3,105.84
Carpet squaresAuditorium install labor, WilliamHis rough guess; price to be confirmed before he starts.$2,200.00
Carpet squares4 pails of carpet-tile glueSame glue as Phase 1, about $137/pail.$548.00
Mini split (Evan's office)TOSOT mini split unit + wall mount bracketPriced, not ordered yet.$849.98
Front signSimple 4×8 double-sided signBudget target, not a quote yet.$2,000.00
Total estimated$8,703.82

⚠ Grand total

Paid + committed + rough estimates still ahead: $40,726.66

Unlisted working page (not in the site menu). Updated 2026-10-26.