- Evan: pick a paint color for your office ASAP so William can paint after the drywall (the nursery will likely just match what's already in use). Open Drywall + room paint →
⚠ Payments coming up
- Reimburse Micheal $100 — he fronted it for William's deposit 11/3.
- Upcoming: $800 to William, the rest of his $1,000 labor, when he finishes the drywall and paint.
- Upcoming: $5,500 to Perry Hudson, the rest of his $11,000, when he finishes the soffit/fascia job.
- Upcoming: $2,500 to Cooper Morgan (Morgan Restoration) for the gutters (half of $5,000), after Perry is on the books.
Next up
- Carpet squaresAfter Phase 1: work out the auditorium price with William
- ElectricalDrill through the walls for the internet and coax runs (Rayburn's hammer drill)
- Gravel parking lot (front)Buy silt fence at Lowe's (for the dirt going on the berm)
- Sewer line to city sewerConfirm with the city: are we already on city sewer?
- Soffit repairGet Perry's signature on the contract
- Roof leakFind a roofer to look at the leak
Projects
Carpet squaresCarpet tiles for the building, done in phases. Phase 1 (foyer and lobby) is finished; the auditorium is next.Auditorium tiles ordered 10/27 · ≈ $6,395 total17 of 25 steps doneOpen →ElectricalOutlets, wall drilling and power the other projects need. Rayburn (volunteer electrician) is helping.Breakers fine · Rayburn helping3 of 4 steps doneOpen →Gravel parking lot (front)Gravel the parking lot: crusher run base (done), #57 stone on top, and now finishing the rest of the lot while Rayburn's equipment is on site.#57 stone coming Mon 11/9 morning7 of 11 steps doneOpen →Sewer line to city sewerDig a new sewer line from the back of the building to the city sewer.Likely on city sewer already · smoke test never happened2 of 7 steps doneOpen →Soffit repairRepair soffit/fascia around the entire building.Perry started 11/2 — back soffit torn off · still waiting on his signed contract back17 of 23 steps doneOpen →Roof leakWater is coming through the roof into the hallway right before the fellowship hall.New · looking for a roofer0 of 1 steps doneOpen →LED lightingSwap old lights for LED as cheaply as possible.ACE Power free audit + TVA rebates0 of 2 steps doneOpen →Drywall + room paintNew drywall in Evan's office and the nursery, then painting both rooms. William is doing the drywall and the painting.William: drywall + paint · $200 deposit paid 11/3, $800 due at completion5 of 11 steps doneOpen →Mini split (Evan's office)Pull the old heater and AC out of Evan's office and put in a ductless mini split, powered off the existing 220V heater circuit.Picked the unit · William running the 220V0 of 4 steps doneOpen →PaintingPainters to quote the building.10 painters to call0 of 1 steps doneOpen →Front signSimple 2-sided sign for now (~$2k), nicer sign later. Try to sell the old one. The church decides.For now ≈ $800–2k · new lit ≈ $10–30k1 of 9 steps doneOpen →Screens & videoTwo big TVs up front and a confidence monitor, with SDI video from the balcony booth — plus a new SDI run to the nursery so they can stream the service there.Equipment arrived · outlet boxes bought · TVs still to buy3 of 7 steps doneOpen →WiFi networkUniFi WiFi for the whole building: one gateway, a PoE switch and 3 ceiling access points.Equipment in, Micheal setting it up · waiting on Ace Fiber install3 of 8 steps doneOpen →Baptistry heaterReplace the baptistry water heater. Plumber from Lexington coming.Little Giant 6HHL 6 kW · replacement on hand0 of 1 steps doneOpen →Chairs & pews~250 cheap chairs; sell the old pews. Low priority.Pews given away 10/29 (to Selmer, TN) · chairs ~$5-7.5k used2 of 6 steps doneOpen →Building & floor planRoom sizes, records, and floor-plan drawings.9,000 sq ft · built 19721 of 2 steps doneOpen →
Completed
Finished projects. Open one to see how it was done, who to call and prices for next time.
All to-dos
Carpet squares
- ✓DoneMeasure, total + 20% overage
- ✓DoneFind best price (compare 6+ suppliers)
- ✓DonePick the tile for Phase 1
- ✓DoneCall Carpet USA: what does "refurbished" mean? (questions on the carpet page)
- ✓DoneOrder Phase 1 tiles (309 tiles / 832 sq ft)
- ✓DoneAsk Carpet USA to correct the shipping ZIP to 38834 (order shows 38835, the P.O. box ZIP)
- ✓DoneCarpet delivered (309 tiles)
- ✓DoneBuy the glue
- ✓DonePick an installer for Phase 1
- ✓DoneBuy the transition strip (carpet tile to vinyl)
- ✓DoneWilliam installs Phase 1
- To doAfter Phase 1: work out the auditorium price with William
- ✓DonePay William for Phase 1 ($400)
- ✓DonePhase 2 (auditorium): confirm the price and freight in the Carpet USA cart (1,556 tiles, ZIP 38834)
- ✓DoneFill the low spot in the slab before William carpets over it (Quikrete Concrete Repair)
- WaitingGet the missing box of tiles (1 of 12 never arrived)
- ✓DoneAsk Carpet USA for a bulk discount on the auditorium order (about 4,200 sq ft / 1,556 tiles)
- ✓DoneOrder the auditorium tiles: 1,556 Refurbished Gray Family Designer Plank (Carpet USA)
- To doBuy 4 pails of the carpet-tile glue (same as Phase 1)
- To doSet the auditorium install dates with William
- WaitingReplacement tiles (20) for the odd-sized ones from Phase 1
- To doAuditorium tiles delivered (1,556): check every box and that all tiles are the same size
- ✓DoneOrder tiles for the toddler room
- To doAsk William to add the toddler room to the auditorium install
- WaitingCarpet USA: refund $91.51 shipping on #262419 and ship it with #262379
Debris removal
- ✓DoneHaul the pile to the dump at 2664 S Harper Rd
Electrical
- ✓DoneRayburn walk-through: both breaker panels and the list on this page
- ✓DoneCheck the breakers
- ✓DoneDecide on the auditorium lights: keep switching at the breakers, or add real switches
- To doDrill through the walls for the internet and coax runs (Rayburn's hammer drill)
Gravel parking lot (front)
- ✓DoneGet 30 tons of crusher run delivered
- To doBuy silt fence at Lowe's (for the dirt going on the berm)
- ✓DoneBill Phillips: 2 loads of crusher run (10/28)
- ✓DoneSubmit the 811 locate request (online at ms811.org)
- ✓DonePut the white flags or paint down: front lot and the sewer trench path
- ✓DoneUtility marks: all 5 utilities responded (Ticket #26102012401223)
- To doFind private lines 811 won't mark (power to the old front sign, water, sewer)
- To do#57 stone on top of the crusher run (after it packs down and gets rained on)
- ✓DoneRayburn digs out the dirt with his backhoe
- WaitingFinish the rest of the lot with Rayburn (beyond the original front-lot scope)
- ✓DoneCall Bill Phillips: heads-up for 2 more crusher run loads + 3 loads of #57
Sewer line to city sewer
- To doConfirm with the city: are we already on city sewer?
- ✓DoneBefore the smoke test: run water in every drain (sinks, floor drains, baptistry drain) and tell anyone in the building
- To doFind out who handles sewer at 170 MS-2 NE (Corinth Gas & Water, or a county utility) and ask what a connection takes
- To doFind where the city sewer line runs behind the building (manhole, street or easement) and measure the trench length
- To doFind out what the building uses now (septic tank?) and what has to happen to it
- ✓Done811 ticket for the sewer trench
- To doGet the connection done (licensed plumber if the city requires it) and inspected
Soffit repair
- ✓DoneGet Perry's corrected contract ($11,000)
- ✓DoneGet Perry's liability insurance
- ✓DoneTom Weaver signs Perry's contract (church side)
- To doGet Perry's signature on the contract
- ✓DonePay Perry $5,500 (half of $11,000) up front
- To doGet Perry's projected finish date once he starts
- To doPay Perry the remaining $5,500 at completion
- ✓DoneCooper: gutters-only estimate in writing ($5,000)
- ✓DoneBobbie (Perry's gutter friend) to call about the gutters
- ✓DonePerry: agree to $11,000 for the fascia, trim and soffit, in writing
- ✓DoneCooper: waiting on answers to our questions
- ✓DoneGet Cooper's quote in writing (soffit/fascia about $10,000; with gutters about $15,000)
- ✓DonePerry Hudson (Hudson Windows & Exteriors): written quote
- ✓DoneLift rental price
- ✓DoneQuestions for Perry before signing (list on this page)
- ✓DoneGet a second quote to compare against $14,500
- ✓DoneB&A Roofing and Gutters: quote requested through their website form
- ✓DoneUniversal Apex Construction & Roofing: called and left a message
- ✓DoneHave the coax and Cat6e cables ready before the soffit crew starts, so they go up inside the soffit
- To doPower-wash the building while the lift is rented
- To doGive Cooper about a week's notice before Perry finishes the fascia
- To doPay Cooper $2,500 (half of $5,000) for the gutters
- ✓DoneReceived the $5,500 check for Perry
Roof leak
- To doFind a roofer to look at the leak
LED lighting
- WaitingCall ACE Power for the free lighting analysis and TVA EnergyRight eligibility
- To doCount fixtures by room (tube length, T12/T8, ballast, dimmers) with photos
Drywall + room paint
- ✓DoneGet Kevin's arrival date
- In progressCheck out the Lowe's cart for the drywall materials
- ✓DoneBuy paint
- ✓DoneMask all the foyer trim before painting
- ✓DoneFind a new drywall contractor for Evan's office and the nursery
- To doGet William's wife's name for the check
- ✓DonePay William $200 up front
- To doGet Evan's paint color choice for his office
- To doBuy paint for the nursery and Evan's office
- To doPay William the remaining $800 when he's done
- To doReimburse Micheal $100 for William's deposit
Mini split (Evan's office)
- To doTake out the old heater and AC unit in Evan's office
- To doBuy the TOSOT 12,000 BTU mini split ($809.99) and wall mount bracket ($39.99)
- To doWilliam runs the 220V up and out the wall where the AC is now
- To doCheck if fire-rated caulk/firestop is needed once the wall is open
Painting
- To doCall painters for quotes
Front sign
- ✓DoneMeasure the width across the top of the lower sign panel
- To doMeasure how deep the sign box edges are (top box and lower panel)
- To doGet the old sign appraised from photos
- To doTry to sell the old sign (Facebook Marketplace, vintage-sign groups, auction)
- To doPrice a simple 4×8 double-sided sign for now (~$2k budget)
- To doLong-term: get 2–3 quotes for the nicer lit sign
- To doGet 1 restore quote to compare
- To doCheck permits with the city
- To doBring the quotes and any sale offer to the church to decide
Screens & video
- ✓DonePick up coax and Cat6 at Lowe's in Corinth
- ✓DoneRoute the coax and Cat6e cable from the booth to the TVs
- To doPut in 2 regular outlets in the wall behind the front TVs
- ✓DoneRSM team: order the equipment (everything but the TVs)
- To doBuy the TVs (2 front TVs + 65″ confidence monitor)
- In progressRun additional SDI (coax) to the nursery so they can stream the service
- In progressPull power for the nursery SDI feed and behind the stage
WiFi network
- To doAnswer the picker questions with Evan (cameras, auditorium puck, outdoor WiFi, speakers)
- To doGet the make and model of the mixer and the wireless snake
- To doConfirm the internet provider and where the modem comes into the building
- ✓DoneWalk the building and mark 3 ceiling spots (auditorium, lobby/office, classroom wing) plus a spare 4th
- ✓DoneRun Cat6 from the switch to each spot (pull the 4th spare cable at the same time)
- ✓DoneRSM team: order the WiFi gear (proposal at the top of this page)
- To doWalk-test signal on a phone; add the 4th access point only if there's a dead spot
- In progressSet up the UniFi gateway, switch and access points
Baptistry heater
- WaitingPlumber visit: swap the heater, check fittings and pump
Chairs & pews
- ✓DonePews: tried to sell, gave them away
- To doTake an after photo of the auditorium without the pews
- To doMark the Facebook Marketplace listing sold
- To doChairs: ask about UsedPews.org lots (120 @ $25, 215 @ $50) and Universal Hotel Liquidators ($19.95)
- ✓DonePews: measure them and post the listing on Facebook Marketplace
- To doTake down the UsedPews.org listing (#11191)
Building & floor plan
- ✓DonePull county parcel / building records
- To doWalk-through sketch of room positions so we can draw a real layout
Real money spent
Actual payments made so far (not budgets or estimates). Running total below.
| Date | Project | What | Amount |
|---|---|---|---|
| 10/14 | Carpet squares | Phase 1 carpet tiles (Carpet USA #261683) | $930.81 |
| 10/22 | Debris removal | Dump runs, 4 loads at 2664 S Harper Rd (3 at $20, 1 at $27) | $87.00 |
| 10/24 | Carpet squares | Phase 1 install, William (invoice #001) | $400.00 |
| 10/27 | Carpet squares | Auditorium carpet tiles (Carpet USA #262379) | $3,646.87 |
| 10/28 | Carpet squares | Toddler room carpet tiles (Carpet USA #262419, incl. $91.51 shipping expected to be refunded) | $313.13 |
| 10/28 | Screens & video | AV equipment (Amazon) | $687.48 |
| 10/28 | Screens & video | Coax cable (Lowe's) | $71.68 |
| 10/28 | WiFi network | UniFi equipment (Amazon, store.ui.com, B&H) + Cat6 cable (Lowe's) | $826.94 |
| 10/29 | Gravel parking lot (front) | Crusher run, 2 loads (Phillips Sand and Gravel #15912) | $1,599.99 |
| 10/31 | Soffit repair | Deposit to Perry Hudson (check #5994) | $5,500.00 |
| 11/3 | Drywall + room paint | William's $200 deposit (drywall/paint) — $100 from selling the church's old Peavey board, $100 fronted by Micheal personally | $200.00 |
| 11/4 | Debris removal | Dump run, 1 load at 2664 S Harper Rd | $20.00 |
| Total spent | $14,283.90 |
Committed, not paid yet
Signed contracts and accepted estimates we owe, but haven't paid out yet. Rough guesses that haven't been confirmed yet are in “Looking ahead” below instead.
| Project | What | Due | Amount |
|---|---|---|---|
| Soffit repair | Remaining balance to Perry Hudson (of his $11,000 contract) | At completion | $5,500.00 |
| Soffit repair | Gutters, Cooper Morgan / Morgan Restoration (estimate #1028, accepted) | After Perry is on the books | $5,000.00 |
| Drywall + room paint | William's labor (drywall + paint, Evan's office and the nursery) | At completion | $800.00 |
| Drywall + room paint | Drywall materials (ToughRock, Gold Bond, mud, tape, screws, ladder) — Lowe's cart ready | At checkout | $1,038.94 |
| Gravel parking lot (front) | Finishing the rest of the lot: 2 more crusher run loads + 3 loads of #57 stone (Phillips), Rayburn's digging/spreading labor | Phillips delivering Mon 11/9 morning; Rayburn finishing after | $5,400.00 |
| Total committed | $17,738.94 |
Looking ahead
Rough estimates and known-but-not-yet-ordered costs — prices can change before these are locked in.
| Project | What | Note | Amount |
|---|---|---|---|
| Screens & video | 2 front 98" TVs (TCL Q6) + 65" confidence monitor (Hisense) | Picked options on the AV page; not bought yet. | $3,105.84 |
| Carpet squares | Auditorium install labor, William | His rough guess; price to be confirmed before he starts. | $2,200.00 |
| Carpet squares | 4 pails of carpet-tile glue | Same glue as Phase 1, about $137/pail. | $548.00 |
| Mini split (Evan's office) | TOSOT mini split unit + wall mount bracket | Priced, not ordered yet. | $849.98 |
| Front sign | Simple 4×8 double-sided sign | Budget target, not a quote yet. | $2,000.00 |
| Total estimated | $8,703.82 |
⚠ Grand total
Paid + committed + rough estimates still ahead: $40,726.66